Viewing inquiries for 03-0G7604

Submit new inquiry for this project


Inquiry #1: On sheet X-1 the Typical Cross Section shows the contractor to Cold Plane AC Pavement (0.15’ Max) from PM 37.6 TO 54.0. In the Special Provisions on page 12, section 39-3.04A states, “At the location listed below, schedule cold planing activities such that the pavement is cold planed, the HMA is placed, and the area is open to traffic during the same work shift: 1. Mainline (PM 37.6 to 54.0)”
On sheet Q-1, Summary of Quantities, Cold Plane AC Pavement, the total only shows 6,452 sy of Conform Grinding.

If the State intends to Cold Plane the entire road way 0.15’ from PM 37.6 to 54.0 the quantity should be +/-230,912 sy of cold planning.

Is it the States intent to cold plane the roadway from PM 37.6 to 54.0 EP to EP 0.15’ Max?

Inquiry submitted 01/31/2018

Response #1:
Your inquiry has been received and is being reviewed.
Response posted 01/31/2018


Response #2:
An addendum has been issued to address this bidder inquiry. Please refer to Addendum No. 2, issued on Friday, February 2, 2018.
Please bid per the current contract documents.
Response posted 02/06/2018




Inquiry #2: The supplemental data provided appears to be a duplicate of EB Lane 1 and WB Lane 1. Also WB Lane 1 has the incorrect stationing per the plans. Please review and provide the correct information.
Inquiry submitted 02/05/2018

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 02/05/2018


Response #2:
Please bid per the current contract documents.
Response posted 02/06/2018




Inquiry #3: With the added quantities of Cold Planning, is it still the states position to Cold Plane, Crack Seal and Place HMA in the same shift as stated in 39-3.04A?
Inquiry submitted 02/05/2018

Response #1:
Your inquiry has been received and is being reviewed. If a response is not posted before bid opening addressing your inquiry, please bid per the current contract documents.
Response posted 02/05/2018


Response #2:
Please bid per the current contract documents.
Response posted 02/06/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.