Inquiry #1: Section 39-2.01C(4)(a) was specifically modified to read that all lanes will be paved to matched up to each other every night. With the tight paving windows this will be a challenge. Can this be changed to read that the adjacent joint will be matched the following shift.
Inquiry submitted 12/11/2017

Response #1:Submitted for consideration.
Response posted 12/13/2017


Response #2:Bid per current contract documents.
Response posted 01/08/2018




Inquiry #2: There are many locations where this highway is damaged beyond the .1' grind. How is Caltrans going to address those issues with out any dig-outs on this project?
Inquiry submitted 12/11/2017

Response #1:Submitted for consideration.
Response posted 12/13/2017


Response #2:Bid per current contract documents.
Response posted 01/08/2018




Inquiry #3: Section 39-2 specifies an overlay thickness of 1.2". The pavement marking material manufacturer required a 1.5" overlay thickness to warranty the stripes, Section 84-5, pg 25. Please clarify.
Inquiry submitted 01/23/2018

Response #1:Please refer to Addendum No.1 dated January 24, 2018.
Response posted 01/25/2018




Inquiry #4: Bid items 15 thru 20 for Striping have no mention of Warranty
In the Specs 84-5 Warranty for Traffic Stripes & Pavement Markings is called out on pages 17-20
Is this really required for this project?

Inquiry submitted 01/23/2018

Response #1:Please refer to Addendum No.1 dated January 24, 2018.
Response posted 01/25/2018




Inquiry #5: The Notice to Bidders states there are 55 Working day to complete this work. With the short work hours and the work to be done in a single shift, 55 WK DA will not be enough time to complete the contract. Please consider increasing the Working Days to 85 Working Days.
Inquiry submitted 01/23/2018

Response #1:Please bid per current contract documents.
Response posted 01/25/2018




Inquiry #6: The new spec for warranty thermo requires a manufacturer's warranty bond for 5 years. Currently, there is only one manufacturer offering this warranty, and they require at least 1.5" overlay or the warranty is void, disqualifying this project for their product. Therefore, there is no way to responsibly bid the thermoplastic striping on this project. Please advise.
Inquiry submitted 01/23/2018

Response #1:Please refer to Addendum No.1 dated January 24, 2018.
Response posted 01/25/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.