Interstate 5 Major Improvement Project

The California Department of Transportation (Caltrans) proposes to improve Interstate 5 between State Route 91 and Interstate 710, a length of approximately 26 kilometers (16 miles), by widening to provide a minimum of 10 lanes. At present, I-5 consists of eight lanes from SR-91 to Beach Boulevard, six lanes from Beach Boulevard to I-605, and eight lanes from I-605 to I-710. The portion of I-5 in Orange County south of SR-91 has been widened to 10 lanes (one High Occupancy Vehicle lane and four mixed flow lanes in each direction with future provisions for 12 lanes).


Environmental Impact Report (EIR/EIS)


Proposed Schedule

>
Interstate 5 Corridor Improvement Project - Subject To Change
Segment Name
Location on I-5
Project Approval Anticipated
Initiate Right of Way Process
Begin Construction
Carmenita Interchange Carmenita Road
March 2003
Winter 2006
Winter 2008
A
State Route 91 to Interstate 605
Summer 2007
Winter 2008
Winter 2010
B
Interstate 605 to Interstate 710
February 2011
February 2013
Winter 2016
C
Interstate 710 Interchange
February 2011
February 2013
Winter 2016

Scoping Summary Report

Download PDF
You can view a full copy of this report at the following locations:
  • Buena Park - Public Works Department, Buena Park Library
  • Commerce - Public Works Department, Atlantic Branch Library, Greenwood Branch Library
  • Downey - Public Works Department, Downey City Library
  • La Mirada - Public Works Department, La Mirada County Library
  • Norwalk - Community Development Department, Norwalk Regional Library, Alondra Library, County of Los Angeles Public Library
  • Santa Fe Springs - Public Works Department, Santa Fe Springs City Library

Below, are the wall graphic summaries for both PUBLIC and AGENCY I-5 scoping meetings for Segment A. The meetings were held on December 3, 2001 and December 5, 2001. All wall graphic summaries are available in PDF format, or viewable with your browser.
Public Agency
December 3, 2001 (PDF) December 3, 2001 (PDF)
December 5, 2001 (PDF) December 5, 2001 (PDF)

Project Map

Project History

Caltrans, in collaboration with the Federal Highway Administration (FHWA), the I-5 Consortium Cities Joint Powers Authority (JPA), Orange County Transportation Authority, Federal Transit Administration and the Los Angeles County Metropolitan Transportation Authority (LACMTA), has completed a Major Investment Study (MIS) to develop improvements for I-5 that would improve mobility and achieve acceptable levels of traffic operation. (An MIS is an integral part of a metropolitan area's long-range planning process that is designed to provide decision-makers with better and more complete information on the options available for addressing identified transportation problems.) The I-5 MIS identified a Locally Preferred Alternative which proposed to widen the existing roadway to a 10 lane, at-grade facility (one High Occupancy Vehicle lane and four mixed flow lanes in each direction). This alternative would also include increases to bus and rail transit services, and Intelligent Transportation Service (ITS) improvements along I-5 and adjacent arterials.

When the MIS was completed in July 1998, funding for the ultimate improvements, the I-5 Major Improvement Project, was not available. The I-5 Interim HOV Project was then initiated in order to assist the declining level of service on the freeway until the ultimate improvements could be implemented. The environmental document for this project was completed in September of 1999 and proposed to add a non-standard HOV lane in each direction of I-5 from SR-91 to Lakewood Boulevard.

In July 2000, Governor Gray Davis signed Transportation Congestion Relief legislation (http://www.dot.ca.gov/dist07/tcrp/tcrp_index.htm), which provided $5.3 billion in critically needed transportation resources to fund more than 100 locally recommended projects throughout California. One of the chosen projects was the ultimate I-5 Major Improvement Project that was studied in the MIS.

Benefits

The I-5 Corridor Improvement Project is intended to improve mobility in the corridor by substantially increasing capacity and improving safety. Some of the immediate benefits are:
  • Elimination of the northbound bottleneck due to the reduction of 5 lanes to 4 lanes between the Orange and LA County lines
  • Performance improvements to major intersections and interchanges
  • Additional capacity to handle the forecasted demands
  • Upgraded I-5 corridor which meets current Caltrans and FHWA design standards
  • Improved access to regional transit and HOV facilities
  • Improved freeway level of service during peak travel hours
  • Reduced travel time delays and congestion-related incidents

Environmental Planning

The I-5 corridor traverses a fully developed urban area with residential and commercial zones immediately adjacent to the freeway. The environmental impacts on the community need to be carefully evaluated. Early public consultation, or scoping will be done to ensure that all stakeholders are involved in the planning process, and that all potential issues are addressed in the environmental document.

Caltrans will be preparing design plans and environmental documents in the following sequence:

  • Interstate 5/Carmenita Road Interchange
  • State Route 91 to Interstate 605 (Finalizing Draft Environmental Document)
  • Interstate 605 to Interstate 710
  • Interstate 5/Interstate 710 Interchange

If you would like to be on the mailing list for one of these projects, please write to one of the following addresses. Be sure to state which segment you are interested in.

By Mail:
  • Mr. Ron Kosinski, Deputy District Director
    Division of Environmental Planning
    120 South Spring Street, MS 16a
    Los Angeles, CA 90012
    Re: I-5 Corridor Improvement Project
By eMail:

Caltrans Contacts

Title Name Phone E-mail
Area Manager Mr. Emad Gorgy (213) 897-6746 Emad.Gorgy@dot.ca.gov
Project Manager Mr. Diaa Yassin (213) 897-0528 Diaa.Yassin@dot.ca.gov
Asst. Project Manager Tarek Soufi (213) 897-4593 Tarek.Soufi@dot.ca.gov

Local City Contacts

Buena Park, Commerce, Downey, La Mirada, Norwalk and Santa Fe Springs (Represented by The I-5 Consortium Cities Joint Powers Authority)

Title Name Phone E-mail
Executive
Director
Yvette Kirrin 310-704-8194 Yvette@kes-inc.com
Authority
Engineer
Yvette Kirrin 310-704-8194 Yvette@kes-inc.com

Project Alternative Maps

The plan sheets of the I-5 Corridor Project from the Orange County Line to the San Gabriel River were presented in public information meetings held in July 2006 in the cities of Santa Fe Springs, La Mirada, and Norwalk. Each plan sheet has 2 alternative designs: a 10-Lane Value Analysis (VA) Alternative and a 12-Lane VA Alternative. The 10-Lane VA Alternative plan sheets show shading for the R/W impacts plus additional shading for the 12-Lane VA Alternative R/W impacts. The 12-Lane VA Alternative plan sheets show the design without any shading of R/W impacts. All the plans are preliminary and the final recommended alternative has not yet been chosen.

Choose 10 or 12 lane alternatives to enable the map.


Page Last Modified 02/27/08 12:59
Back Button | Back To Page Top Link