Contract 10-0F85U4
The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.
Q1) Section 4, why only 45 days when previous jobs of this sort would allow 165 working days? 45 days will add greatly to the State’s cost.
A) Please refer to Addendum No. 1, dated May 18, 2006.
Q2) Section 10-1.13 Temp Fence Chain Link, job is WM. Why C/L for temp fence?
A) Please refer to Addendum No. 1, dated May 18, 2006.
Q3) Section 10-1.15 Pull post specified as 100 meters. State standards approx. 200 meters. Is the 100 designation a typo error?
A) Please refer to Addendum No. 1, dated May 18, 2006.