California State Department of Transportation

Project Development Workflow Tasks (PDWT)

PYPSCAN Milestone 300

Circulate Plans for Review

(Click on highlighted Task to see detailed information.)

Design
Task
Number

Design Tasks (D388-D416) 

Milestone
Task Group
 
 Last Update

D388
Prepare Final Project Plans

(300.A)

11/28/94

D389
Prepare Construction Traffic Handling Plan

(300.A)

11/28/94

D390
Prepare Pavement Delineation Plans

(300.A)

11/28/94

D391
Complete Drainage Plans

(300.A)

11/28/94

D392
Calculate Final Quantities

(300.A)

11/28/94

D393
Complete Electrical Portion of the PS&E

(300.A)

11/28/94

D394
Complete Landscape PS&E

(300.A)

11/28/94

D395
Prepare Final Plans for Landscape Review

(300.A)

11/28/94

D396
Prepare Detour, Traffic Handling, and Temporary Connection Plans

(300.A)

11/28/94

D397
Review Components of the Traffic Plan

(300.A)

11/28/94

D398
Obtain Local Entities Review of Road Closures

(300.A)

11/28/94

D399
Prepare Final Railroad Plans and Agreements

(300.B)

11/28/94

D400
Obtain Right of Way Information for PS&E

(300.C)

11/28/94

D401
Review Right of Way Contractual Obligations

(300.C)

11/28/94

D402
Prepare Draft PS&E Package

(300.D)

11/28/94

D403
Identify Recyclable Materials

(300.D)

11/28/94

D404
Obtain Approval to Use Trade Name Items

(300.D)

11/28/94

D405
Send Project Plans to Local Entities for Review

(300.D)

11/28/94

D406
Prepare Survey File

(300.D)

11/28/94

D407
Complete Project Plans

(300.D)

11/28/94

D408
Prepare Final Estimate of Cost

(300.D)

11/28/94

D409
Conduct Project Safety Review

(300.E)

11/28/94

D410
Prepare Safety Review Report

(300.E)

11/28/94

D411
Prepare Materials Information Handout

(300.F)

11/28/94

D412
Conduct Environmental Reevaluation

(300.F)

11/28/94

D413
Request Final Permits Review

(300.F)

11/28/94

D414
Prepare Draft Special Provisions

(300.G)

11/28/94

D415
Complete PS&E Cover Memorandum and Attachment "A"

(300.G)

11/28/94

D416
Request Final Environmental Review

(300.H)

11/28/94

Go to Top of Document


TASK D388 (300.A)

Prepare Final Project Plans

Narrative

Skeleton layouts have been completed and used to prepare geometrics. The final plans should now be developed.

Initiator

Sub-Tasks

NOTE: Final project plans must be consistent with the project description identified during the environmental process, in the Final environmental document and environmental reevaluations.

Task Duration

References

Go to Top of Document


TASK D389 (300.A)

Prepare Construction Traffic Handling Plan

Narrative

The Construction Traffic Handling Plan uses data from the lane requirement charts previously prepared. The plan includes temporary lane closure charts, half-width construction, and other traffic control procedures that will comply with the scheduled windows for lane closures that were identified in the lane requirement charts. The Project Engineer leads this activity with the help of the Traffic Unit.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D390 (300.A)

Prepare Pavement Delineation Plans

Narrative

The preliminary Pavement Delineation Plans were prepared on skeleton layouts so that support functions of the Traffic Unit could prepare their portion of the project PS&E. Final Pavement Delineation Plans should now be prepared. The Project Engineer leads this activity with the help of the Traffic Unit.

Initiator

Sub-Tasks

- Lane delineation

- Shoulder and gore striping

- Pavement markers

- Crosswalks

- Channelization

- Other pavement markings (school zones, etc.)

Task Duration

References

Go to Top of Document


TASK D391 (300.A)

Complete Drainage Plans

Narrative

Preparation of Drainage Plans has been underway since the beginning of hydrology studies. The final Drainage Plans should now be prepared.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D392 (300.A)

Calculate Final Quantities

Narrative

Functional units calculated quantities when preparing their portion of the project PS&E. The Project Engineer calculated other quantities for the project. The Project Engineer should now finalize the quantities and review quantities prepared by functional units.

Initiator

Sub-Tasks

- Miscellaneous

- Sanitary sewer

- Drainage

- Earthwork

- Structural section

- Hazardous waste remediation (if included in the highway contract)

- Right of way obligations to be included in the contract, etc.

Task Duration

References

Go to Top of Document


TASK D393 (300.A)

Complete Electrical Portion of the PS&E

Narrative

Preliminary Pavement Delineation Plans were sent to the Traffic Unit at the beginning of electrical design. Subsequently, the Project Engineer made a final review. The Traffic Unit should now complete the electrical portion of the project PS&E.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D394 (300.A)

Complete Landscape PS&E

Narrative

Water supply and electrical power sources have been determined. Other relevant landscape features should now be identified so that the landscape portion of the PS&E can be completed.

Initiator

Sub-Tasks

NOTE: If landscaping was included for environmental mitigation, it should be reviewed by the Environmental Unit.

Task Duration

References

Go to Top of Document


TASK D395 (300.A)

Prepare Final Plans for Landscape Review

Narrative

Items included in the Landscape PS&E may impact other project features. The Landscape Unit should now review the final project plans.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D396 (300.A)

Prepare Detour, Traffic Handling, and Temporary Connection Plans

Narrative

Preliminary plans for detours, temporary connections, stage construction, etc. were prepared and sent to functional units for use in preparing their portion of the PS&E. Final plans for these features should now be prepared.

Initiator

Sub-Tasks

- Traffic Management Plan

- Construction Staging Plan

- Lane closure charts

- Preliminary Pavement Delineation Plan

- Length of work periods

- Work schedules impacting traffic

- Feasibility of night/weekend construction

- Any special conditions

Task Duration

References

Go to Top of Document


TASK D397 (300.A)

Review Components of the Traffic Plan

Narrative

Traffic Units began work on their components of the PS&E after skeleton layouts were available. Each component should now be complete and reviewed as the total Traffic Plan.

Initiator

Sub-Tasks

- Pavement Delineation

- Traffic Electrical

- Traffic Lighting

- Traffic Signing

- Traffic Handling

Task Duration

References

Go to Top of Document


TASK D398 (300.A)

Obtain Local Entities Review of Road Closures

Narrative

Local entities have been involved in the project's development since the early stages. Execution of the Freeway Agreement formalized their concurrence with proposed modifications to local roads, including: road closures, interchanges, separations, frontage roads, and cul-de-sacs. Local entities should now be requested to review temporary road closures that may occur during construction.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D399 (300.B)

Prepare Final Railroad Plans and Agreements

Narrative

Division of Structures obtained approval of railroad features during development of the Structure General Plans and a participation estimate was prepared, if appropriate. The final Railroad Plans and Agreements must now be prepared.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D400 (300.C)

Obtain Right of Way Information for PS&E

Narrative

The Right of Way Branch is requested to furnish an update on the Right of Way Certification and a final list of right of way contractual obligations to be included in the project.

Initiator

Sub-Tasks

For "No. 3" Right of Way Certification, the Right of Way Branch should indicate when a "No. 1" or "No. 2" certification will be available. For a "No. 3" certification with "Work-arounds", the Right of Way Branch should also furnish work-around details.

Task Duration

References

Go to Top of Document


TASK D401 (300.C)

Review Right of Way Contractual Obligations

Narrative

Right of way contractual obligations were identified when the Right of Way Contracts were executed. The Project Engineer must now review these contracts to verify the calculations performed under Task D376.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D402 (300.D)

Prepare Draft PS&E Package

Narrative

The draft PS&E Package, which is part of the PS&E Submittal is now prepared. The submittal consists of (1) the PS&E package, (2) other documents "Under Separate Cover," and (3) component project plans. The "Plans, Specifications and Estimate Guide" describes the contents of the submittal.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D403 (300.D)

Identify Recyclable Materials

Narrative

The FHWA and Caltrans Recycling Program policies reflect a strong commitment. Materials that can be reused on the same project or stored for a future project include: existing pavement, guardrails, electrical hardware, etc. The Project Engineer must now proceed with the tasks outlined in the District Recycling Program and by Caltrans policy memorandum P78-17 (Revised).

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D404 (300.D)

Obtain Approval to Use Trade Name Items

Narrative

Caltrans policy permits any brand of a manufactured product to be used on a project, if it meets the standard specifications for contract items of work. There may be projects that require the use of trade name products that are not found in the standard specifications; for example: a specific type of manhole and cover designed for a local facility. If a trade name product is not included in the standard specifications, adequate justification and approval must be obtained for use in the contract.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D405 (300.D)

Send Project Plans to Local Entities for Review

Narrative

The project features have been reviewed by local entities throughout the project development process. Geometrics, structural sections, and preliminary plans also have been reviewed. Project plans should now be sent to local entities for review.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D406 (300.D)

Prepare Survey File

Narrative

The Project Engineer has been accumulating survey data since project initiation. The data includes field surveys performed by the Survey Unit, as well as survey related calculations performed by the Project Squad. The Project Engineer should now use this data to prepare a Survey File for use in construction surveys.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D407 (300.D)

Complete Project Plans

Narrative

The project plans were sent for review to local entities. The plans consisted of Roadway, Drainage, Contour Grading, Traffic, Landscape, Electrical, Structure General Plans and Walls, and quantities lists and details. They must be revised for inclusion in the PS&E submittal.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D408 (300.D)

Prepare Final Estimate of Cost

Narrative

The project plans have been completed. The next step in completing the PS&E is to prepare the final estimate of cost.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D409 (300.E)

Conduct Project Safety Review

Narrative

The District Safety Review Committee conducts a formal Safety Review of projects costing over $300,000. Other projects are reviewed informally. The review should occur as early as possible, to allow time to make corrections prior to project plan completion. The purpose of the review is to consider safety issues during and after construction.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D410 (300.E)

Prepare Safety Review Report

Narrative

After the Safety Review has been conducted by the District Safety Review Committee, a Safety Review Report should be prepared. The report is not attached to the PS&E package, but a reference is included stating that the report has been prepared and that its recommendations have been considered.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D411 (300.F)

Prepare Materials Information Handout

Narrative

The Materials Information Handout is prepared for the use of prospective bidders. The handout includes test data on local materials sources, soil survey sheets showing borings, tests, and seismic information. It also includes a statement that the project conforms with environmental law and regulations for noncommercial borrow, disposal, or material sites.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D412 (300.F)

Conduct Environmental Reevaluation

Narrative

The environmental reevaluation process determines if changes have occurred during design that may have environmental impacts not addressed in the Final environmental document.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D413 (300.F)

Request Final Permits Review

Narrative

The permit process has been considered since project initiation. A project may be stopped or delayed by entities with approval rights or the authority to issue permits.

Initiator

Sub-Tasks

- All permits have been issued

- Approval conditions in each permit have been complied with in the PS&E or handled otherwise

- Expiration dates are current

Task Duration

References

Go to Top of Document


TASK D414 (300.G)

Prepare Draft Special Provisions

Narrative

The specifications for a Caltrans construction contract include the Standard Specifications and Standard Special Provisions (SSPs) specifically written for that contract. The Standard Specifications provide the requirements for bidding, construction, and administration of Caltrans contracts.

Special Provisions provide the legal, administrative, and technical contract requirements applicable to a specific project, by:

- Incorporating, amending, and supplementing Caltrans' published Standard Specifications

- Incorporating legal, administrative, and technical contract requirements not covered by the Standard Specifications

All contract work to be performed must be identified in the Contract Special Provisions.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D415 (300.G)

Complete PS&E Cover Memorandum and Attachment "A"

Narrative

The PS&E Cover Memorandum and Attachment "A" contain information, documentation, and Right of Way certification required prior to project advertising.

Initiator

Sub-Tasks

Task Duration

References

Go to Top of Document


TASK D416 (300.H)

Request Final Environmental Review

Narrative

Environmental assessments occur throughout the planning and design phases of a project. During the early phases of design, the project was reevaluated to determine if a Supplemental Project Report - and possible additional environmental assessment - would be required. The hazardous waste remediation process and permit requirements may also impact final requirements for mitigating environmental effects.

Initiator

Sub-Tasks

- Environmental commitments

- Hazardous waste remediation requirements

- Material sites

Task Duration

References

Go to Top of Document

 PDWT Home Page

 Index

PDPM Home Page

Design Program Home Page

Caltrans Home Page

For questions or feedback concerning this web site email:

trmail1.bhickox@trmx3.dot.ca.gov


This web site last modified August 12, 1997.

Go to Top of Document