California State Department of Transportation
|
000 Identify Project Need and Begin Project
Studies
(Planning Tasks P001-P044)
010 Approve Project Study Report
(Planning Tasks P045-P075)
020 Initiate Environmental Studies
(Planning Tasks P076-P141)
040 Initiate Draft Project Report and Draft
Environmental Document
(Planning Tasks P142-P155)
060 Circulate Draft Project Report and Draft
Environmental Document in District
(Planning Tasks P156-P160)
100 Approve Draft Project Report
(Planning Tasks P161-P172)
120 Circulate Draft Environmental Document
(Planning Tasks P173-P179)
140 Conduct Public Hearing
(Planning Tasks P180-P186)
160 Approve final Environmental Document
(Planning Tasks P187-P211)
200 Approve Initiation of PS&E
(Design Tasks D212-D265)
220 Complete Geometric Base Maps
(Design Tasks D266-D307)
221 Send Bridge Site Data to Structures Design
(Design Tasks D308-D312)
222 Initiate Structures Design
(Design Tasks D313-D315)
224 Send Maps to Right of Way Engineering
(Design Tasks D316-D321)
225 Initiate Right of Way Appraisals
(Design Task D322)
260 Distribute Skeleton Layouts to Functional
Units
(Design Tasks D323-D364)
265 Send Final Maps to Right of Way
(Design Tasks D365-D378)
275 Send Structures General Plan to District
(Design Tasks D379-D387)
300 Circulate Plans for Review
(Design Tasks D388-D416)
360 Complete Environmental Reevaluation
(Design Task D417)
*377 Complete PS&E and send to District
Office Engineer
(Design Tasks D418, D420, D421)
378 Send Structures PS&E to District
(Design Task D419)
380 Send District PS&E to Office of Office
Engineer
(Design Tasks D422-D425)
410 Obtain Right of Way Certification
(Design Tasks D426-D427)
*420 Complete Special Provisions
(Design Tasks D428-D429)
460 Determine Contract is Ready to List for
Advertising
(Design Task D430)
480 Advertise Contract
(Design Tasks D431-D434)
500 Approve Contract
(Design Tasks D435-D436)
600 Complete Construction Project
(Design Task D437)
700 Prepare Final Project Files
(Design Tasks D438-D439)
* Milestones 377 and 420 are not PYPSCAN Milestones. They were added to reflect the Office Engineer function in the Districts and Headquarters.
![]()