Chronology 1999
|
March 1999 |
Issued Project Management Directive 99-01 Project
Management Definitions. |
|
March 1999 |
Issued Project Management Directive 99-03 Project
Management Roles. |
|
March 1999 |
Issued Project Management Directive 99-04 Capital
Project Operational Plans. |
|
April 1999 |
Publish the Project Management Handbook,
Third Edition |
|
May 1999 |
Issued Project Management Directive 99-02 Project
Identification. |
|
May 1999 |
Revised Work Breakdown Structure (WBS 4.0 May 1999)
for 98/99 FY to deal with Program Accountability
at Caltrans (PACT) and realignments of R/W Property
Management & Excess Land Sales. |
|
June 1999 |
Selected alternatives for Capital Project Initiation,
Cost and Schedule Management and provided a Project
Management framework, function hierarchy, process
flow diagrams, data requirements, and glossary for
Capital Outlay Support in Designer 2000. |
|
June 1999 |
Instructions issued for reimbursement of Project
Management Professional (PMP) Certification costs.
|
|
June 1999 |
STATEWIDE PROJECT MANAGEMENT IMPROVEMENT TEAM ADOPTS
A 5-POINT VISION, June 8, 1999
- Integrated and standardized project management
database system.
- Continuous and adaptable project management
training program.
- Functional areas use workplans to plan, guide
execution and status their work.
- Caltrans is a recognized leader in project
delivery quality (ISO 9000).
- Project manager career path.
|
|
July 1999 |
Using funds in 1998-99 budget (see July 1998), Caltrans
provided over 400,000 hours of training to its Capital
Outlay Support employees. |
|
July 1999 |
Developed and updated interrelated tables from Project
Management Control System (PMCS), eXpert Project
Manager (XPM), California Transportation Improvement
Program System (CTIPS) and the Operations Plan for
a project cost and schedule management system to
guide development of a quarterly reporting system.
|
|
July 1999 |
Developed a prototype visual fox pro system that
allows the operations plan manager to manage the
operations plan. The system will need to include
all of the functionality to add and remove projects,
maintain a baseline, and manage the linkages to
program project counterparts as well as maintain
links to eXpert Project Manager (XPM) and Project
Management Control System (PMCS). This system should
include input procedures and processes to maintain
PMCS data as well. One result will be data that
can be warehoused for ease of access to internal
and external customers. |
|
August 1999 |
Project Schedule Control System (PSCS) User Manual.
User's manual for generating eXpert Project Manager
(XPM)/Time Reporting System (TRS) comparison reports.
|
|
September 1999 |
Caltrans creates two Project Management Coordinators
positions to improve communication between Headquarters
and the District's in regards to Capital delivery
expectations and project management best practices.
Revised Capital Projects Milestones 09/13/99. Engineering
Service Center Changes requested July 7, 1999. |
|
October 1999 |
AB1012 10/10/99
AB 1012 contains seven main elements and is an urgency measure.
The main intent of the bill is to reduce the large cash balance in the
State Highway Account in the State Transportation Fund.
AB1012 has seven major components as follows:
- Transportation Project Delivery Advisory Teams
- Comprehensive Project Delivery Management
Information System Plan
- Adds an "Advance Project Development" Element
to the STIP and Requires Fund Estimate to Designate
Resources Available for Advance Project Development
Element
- Reimbursable Work Account
- State Highway Account (SHA) Loan Program
- Expedited Project Study Report (PSR) Compliance
- Regional Surface Transportation Program (RSTP)-Congestion
Mitigation & Air Quality Improvement Program
(CMAQ)/Obligational Authority "Use-it-or-Lose-It"
Limitation.
|
|
November 1999 |
Annual Review of Project Scope, Cost and Schedule
11/22/99. Project Managers shall ensure that each
project has a documented review and update of the
project's scope, cost and schedule, which is not
more than one year old, included in the project's
permanent history file. |
|
December 1999 |
Issued Project Management Directive 99-05 Planning,
producing and charging by Phase.
35 subject matter experts participated in a one-week
workshop to design a skill development plan for
the entire 10,000-person capital project workforce.
|